152 Berry St

San Francisco permit 202407317678 · Mission Bay

Commercial or tenant improvementFull plan reviewComplete
Street view · Feb 2025
Google Street View of 152 Berry St, Feb 2025
Scope of work
As written on the permit application.

Change occupancy type e to i-4. exterior paly yard- new gate, accessibility improvement in restrooms.

Timeline
Key dates from the city record.
Filed
Sep 17, 2024
Issued
Oct 25, 2024 (1 month after filing)
Completed
Nov 22, 2024 (within 1 month of issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 7 departments
Comments issued
Twice, by Building Inspection, Fire Department
Review stopFinishedResult

Apartment and hotel inspection

Building Inspection · HIS

Jul 31, 2024Administrative

Intake

Building Inspection · INTAKE

Jul 31, 2024Administrative

Zoning review

Planning · CP-ZOC

Aug 13, 2024Not Applicable

Mechanical and energy plan review

Building Inspection · MECH

Aug 13, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 13, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 13, 2024Approved

Public health review

Public Health · HEALTH

Aug 13, 2024Not Applicable

Mechanical and energy plan review

Building Inspection · MECH

Aug 22, 2024Approved

Permit Center

Permit Center · PERMIT-CTR

Sep 12, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Sep 6, 2024Not Applicable

Mechanical pre-screening

Building Inspection · PRE-MECH

Sep 9, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Sep 10, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Sep 18, 2024Administrative

Redevelopment review

Redevelopment · REDEV

Oct 10, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 11, 2024Approved

Fire prevention review

Fire Department · SFFD

Sep 20, 2024—

Permit Processing Center

Building Inspection · PPC

Oct 22, 2024Administrative

Fire prevention review

Fire Department · SFFD

Sep 20, 2024Approved

Redevelopment review

Redevelopment · REDEV

Oct 15, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 15, 2024Approved

Fire prevention review

Fire Department · SFFD

Oct 16, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 18, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Oct 25, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$10,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Lisa Jay Gelfand

Gelfand Partners Architects

ArchitectC17265
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202407317678 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record