633 Arguello Bl
San Francisco permit 202407317683 · Inner Richmond
Erect 4 stories type va over 1a basement, 4 unit residential building
- Filed
- Sep 26, 2024
- Issued
- Dec 11, 2025 (14 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 79 stops across 6 departments
- Comments issued
- 24 times, by Permit Center, Building Inspection, Public Works, Public Utilities, Fire Department
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 30, 2024 | Aug 9, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 5, 2024 | Aug 5, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 5, 2024 | Aug 5, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Aug 8, 2024 | Aug 8, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 4, 2024 | Sep 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 5, 2024 | Sep 26, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 26, 2024 | Nov 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 26, 2024 | Nov 1, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2024 | Oct 11, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Sep 26, 2024 | Oct 9, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 26, 2024 | Oct 3, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 26, 2024 | Jun 20, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Sep 27, 2024 | Oct 23, 2024 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Sep 27, 2024 | Sep 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 20, 2024 | Jan 14, 2025 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Dec 2, 2024 | Dec 2, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 16, 2024 | Jan 3, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 16, 2024 | Jan 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 16, 2024 | Dec 26, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 16, 2024 | Jan 7, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 16, 2024 | Dec 17, 2024 | Approved-Stipulated |
Public Utilities programs review Public Utilities · SFPUC-PRG | Dec 16, 2024 | Dec 16, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Mar 25, 2025 | May 15, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 25, 2025 | May 28, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2025 | Mar 31, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 25, 2025 | Jun 3, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 25, 2025 | Mar 26, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Mar 25, 2025 | Apr 15, 2025 | Approved-Stipulated |
Public Utilities programs review Public Utilities · SFPUC-PRG | Mar 25, 2025 | Mar 31, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 23, 2025 | Apr 28, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 23, 2025 | Apr 28, 2025 | Approved-Stipulated |
Public Utilities programs review Public Utilities · SFPUC-PRG | Apr 25, 2025 | Apr 25, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jun 20, 2025 | Jun 20, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Jun 20, 2025 | Jun 20, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 20, 2025 | Dec 11, 2025 | Administrative |
Addendum 1: Shoring, foundation, superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 30, 2025 | Jan 21, 2026 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Dec 31, 2025 | Mar 13, 2026 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jan 27, 2026 | Feb 17, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 16, 2026 | Apr 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 16, 2026 | Apr 22, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 16, 2026 | Apr 22, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 16, 2026 | Mar 26, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Mar 16, 2026 | Mar 17, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 16, 2026 | Apr 23, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 16, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Aug 17, 2026 | Aug 17, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Aug 17, 2026 | Aug 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 26, 2026 | Sep 3, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 26, 2026 | Aug 26, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Oct 1, 2026 | Oct 1, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Oct 9, 2026 | Oct 9, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 2: Architectural, and mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 30, 2025 | Jan 21, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Feb 19, 2026 | Mar 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 5, 2026 | Mar 5, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 5, 2026 | Apr 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 5, 2026 | Apr 21, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 5, 2026 | Mar 20, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 5, 2026 | Mar 24, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 5, 2026 | Jul 10, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 5, 2026 | Apr 14, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 5, 2026 | Mar 10, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Mar 5, 2026 | Mar 5, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 5, 2026 | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | Apr 21, 2026 | Apr 21, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jun 30, 2026 | Jul 7, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2026 | Jul 10, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jul 2, 2026 | Jul 2, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 9, 2026 | Jul 9, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 20, 2026 | Sep 4, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 9, 2026 | Oct 9, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $2,400,000
| Name | Role | License on permit |
|---|---|---|
| Edward Davis Morris Kerman Morris Architects | Architect | 24585 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025