550 Terry A Francois Bl
San Francisco permit 202408057917 · Mission Bay
The entire north tower roofing will be removed down to the slab and replaced. the existing rooftop ahu will be removed and replaced inkind. a new door will be added as an exit for the 4th floor terrace.
- Filed
- Aug 5, 2024
- Issued
- Oct 11, 2024 (2 months after filing)
- Completed
- Jun 11, 2025 (8 months after issuance)
- Review stops
- 11 stops across 3 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 5, 2024 | Aug 5, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Aug 5, 2024 | Aug 5, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 5, 2024 | Aug 5, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 5, 2024 | Aug 5, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 21, 2024 | Aug 21, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 21, 2024 | Aug 21, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 27, 2024 | Aug 27, 2024 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Aug 27, 2024 | Aug 27, 2024 | Not Applicable |
Electrical plan review Building Inspection · MECH-E | Sep 4, 2024 | Sep 4, 2024 | Approved |
Redevelopment review Redevelopment · REDEV | Sep 24, 2024 | Sep 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 11, 2024 | Oct 11, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $3,238,165
| Name | Role | License on permit |
|---|---|---|
| Wright J Sherman Wrns Studio | Architect | C27048 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026