527 30th St
San Francisco permit 202408057976 · Glen Park
Interior remodel. addition of two dormer. new greywater system. new and replacement windows, doors and skylights.excavation and underpinning not affecting the slope stability and therefore not requiring geotech and geological reports at the pre-plan check stage per dbi mgmt review.
- Filed
- Sep 12, 2024
- Issued
- Apr 10, 2025 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 28 stops across 5 departments
- Comments issued
- 10 times, by Permit Center, Building Inspection, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 1, 2024 | Aug 14, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Aug 9, 2024 | Aug 9, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 12, 2024 | Aug 12, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Aug 29, 2024 | Sep 12, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 10, 2024 | Sep 10, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 13, 2024 | Sep 13, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 13, 2024 | Sep 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 13, 2024 | Nov 13, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 13, 2024 | Oct 2, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 13, 2024 | Sep 16, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 13, 2024 | Sep 13, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 13, 2024 | Feb 11, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Oct 2, 2024 | Oct 2, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2024 | Oct 11, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 14, 2024 | Oct 14, 2024 | Issued Comments |
Mechanical plan review quality control Building Inspection · MECH-QC | Oct 15, 2024 | Oct 15, 2024 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Nov 13, 2024 | Nov 13, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jan 23, 2025 | Jan 30, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 23, 2025 | Feb 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 23, 2025 | Jan 27, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 23, 2025 | Jan 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 23, 2025 | Jan 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2025 | Jan 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 3, 2025 | Feb 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 3, 2025 | Feb 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 3, 2025 | Feb 6, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 3, 2025 | Feb 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 11, 2025 | Apr 10, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $450,000
| Name | Role | License on permit |
|---|---|---|
| Karen F Curtiss Red Dot Studio Architecture | Architect | C-31453 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025