45 Walnut St
San Francisco permit 202408078157 · Presidio Heights
1/f: remove (e) garage stairs, move garage wall, add new gym rm, reconfigure (e) bath. remove (e) back staircase, add new staircase to 2/f. 2/f: move (e) powder room, move (e) kitchen to open into new sitting room, new pantry. remove (e) back staircase to 1/f. 3/f: add new walk-in closet to
- Filed
- Aug 7, 2024
- Issued
- Oct 4, 2024 (2 months after filing)
- Completed
- Dec 16, 2025 (14 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 9 stops across 4 departments
- Comments issued
- Once, by Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 7, 2024 | Aug 7, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 7, 2024 | Aug 7, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 14, 2024 | Aug 14, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 22, 2024 | Aug 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 22, 2024 | Aug 22, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 22, 2024 | Aug 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 22, 2024 | Aug 22, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Aug 22, 2024 | Aug 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2024 | Oct 4, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $255,000
| Name | Role | License on permit |
|---|---|---|
| Steven Carl Geiszler Geiszler Architects | Architect | C24557 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022