418 Liberty St
San Francisco permit 202408088241 · Castro/Upper Market
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Rev to pa# 202209212864, pa# 20221298030 & pa# 202210275300 to change e.o.r. & include revision to replace building foundation with mat slab & replace retaining wall @ garage to backyard transition. minor revision to shear wall length & beam sizes @ upper floors. minor revision to framing details.
- Filed
- Sep 23, 2024
- Issued
- Dec 20, 2024 (3 months after filing)
- Completed
- Mar 26, 2026 (15 months after issuance)
- Review stops
- 15 stops across 3 departments
- Comments issued
- 4 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 6, 2024 | Aug 21, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Aug 8, 2024 | Aug 8, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Aug 8, 2024 | Sep 24, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 13, 2024 | Aug 13, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 15, 2024 | Aug 15, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Sep 11, 2024 | Sep 23, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 20, 2024 | Sep 20, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 23, 2024 | Sep 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 24, 2024 | Nov 10, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 24, 2024 | Sep 25, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 24, 2024 | Dec 18, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 4, 2024 | Dec 4, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 5, 2024 | Dec 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 6, 2024 | Dec 17, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 18, 2024 | Dec 20, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| James William Zack Zack/Devito Architecture | Architect | C24446 |
| Randy Edward Collins Ftf Engineering, Inc | Engineer | S4802 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025