1740 Sanchez St
San Francisco permit 202408088265 · Glen Park
1/f: remove e) garage, create new reconfifing garage, bedroom, bathroom & stair. 2nd/f: convert (e) living rm to 1 bedroom, family rm to 1 bedroom. remove (e) dining room and create (n) bathroom and dining room. remodel (e) kitchen. remove (e) bathroom to create new kids area. remove (e) dining room
- Filed
- Oct 1, 2024
- Issued
- Mar 12, 2025 (5 months after filing)
- Completed
- Aug 6, 2026 (17 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 25 stops across 5 departments
- Comments issued
- 8 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 8, 2024 | Aug 8, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 8, 2024 | Aug 8, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Aug 20, 2024 | Aug 30, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 27, 2024 | Aug 27, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Aug 28, 2024 | Aug 28, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 29, 2024 | Aug 29, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Sep 16, 2024 | Sep 30, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 30, 2024 | Sep 30, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 30, 2024 | Sep 30, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 1, 2024 | Oct 1, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 1, 2024 | Nov 7, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 1, 2024 | Oct 16, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 1, 2024 | Nov 4, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 1, 2024 | Oct 2, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 1, 2024 | Feb 27, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 15, 2025 | Jan 23, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 15, 2025 | Jan 15, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 15, 2025 | Jan 16, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 15, 2025 | Jan 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 14, 2025 | Feb 19, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 14, 2025 | Feb 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 14, 2025 | Feb 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 14, 2025 | Feb 18, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 24, 2025 | Feb 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 27, 2025 | Mar 12, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $428,075
| Name | Role | License on permit |
|---|---|---|
| Bo Zhang Ladc Engineering Inc | Engineer | C82956 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2011