225 Stanyan St
San Francisco permit 202408098327 · Lone Mountain/USF
Remove portion of structure walls, create larger kitchen. convert (e) living room to a bedroom with bathroom.
- Filed
- Sep 3, 2024
- Issued
- May 8, 2025 (8 months after filing)
- Completed
- May 7, 2026 (12 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 30 stops across 3 departments
- Comments issued
- 17 times, by Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 8, 2024 | Aug 28, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 14, 2024 | Aug 14, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Aug 15, 2024 | Aug 15, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 16, 2024 | Aug 16, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Aug 23, 2024 | Aug 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 30, 2024 | Sep 4, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Sep 4, 2024 | Oct 16, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 4, 2024 | Sep 20, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 4, 2024 | Sep 16, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 4, 2024 | May 6, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Oct 29, 2024 | Nov 20, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 29, 2024 | Oct 31, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 29, 2024 | Dec 3, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 20, 2024 | Jan 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2024 | Dec 23, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 20, 2024 | Dec 31, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 3, 2025 | Jan 6, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 3, 2025 | Jan 9, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 27, 2025 | Jan 27, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 3, 2025 | Feb 18, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 19, 2025 | Feb 19, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 17, 2025 | Mar 17, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 19, 2025 | Mar 19, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 21, 2025 | Mar 21, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 4, 2025 | Apr 10, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 16, 2025 | Apr 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 17, 2025 | Apr 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 17, 2025 | Apr 22, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 17, 2025 | Apr 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 6, 2025 | May 8, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $185,000
| Name | Role | License on permit |
|---|---|---|
| Fumio Suda Fumio Suda Architect | Architect | C20336 |
| Marcus Yan Design Everest Consulting | Engineer | C83553 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022