CheckMyDesigner

225 Stanyan St

San Francisco permit 202408098327 · Lone Mountain/USF

Home remodelFull plan reviewComplete
Street view · Dec 2022
Google Street View of 225 Stanyan St, Dec 2022
Scope of work
As written on the permit application.

Remove portion of structure walls, create larger kitchen. convert (e) living room to a bedroom with bathroom.

Timeline
Key dates from the city record.
Filed
Sep 3, 2024
Issued
May 8, 2025 (8 months after filing)
Completed
May 7, 2026 (12 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
30 stops across 3 departments
Comments issued
17 times, by Building Inspection, Public Utilities
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Aug 28, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Aug 14, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Aug 15, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Aug 16, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Aug 23, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Sep 4, 2024Administrative

Building plan review

Building Inspection · BLDG

Oct 16, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 20, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Sep 16, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

May 6, 2025Administrative

Building plan review

Building Inspection · BLDG

Nov 20, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 31, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Dec 3, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jan 9, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 23, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Dec 31, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 6, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jan 9, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jan 27, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 18, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Feb 19, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Mar 17, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Mar 19, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 21, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Apr 10, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 16, 2025Approved

Building plan review

Building Inspection · BLDG

Apr 17, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 22, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 22, 2025Approved

Central Permit Bureau

Building Inspection · CPB

May 8, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$185,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Fumio Suda

Fumio Suda Architect

ArchitectC20336
Marcus Yan

Design Everest Consulting

EngineerC83553
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202408098327 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record