1240 Valencia St
San Francisco permit 202408098357 · Mission
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Rev 201912139558- to renovate (e) site ada ramp and bike racks facing front of building. scope includes (n) 3 ft play area fence located at front
- Filed
- Sep 10, 2024
- Issued
- Dec 23, 2024 (3 months after filing)
- Completed
- Mar 26, 2025 (3 months after issuance)
- Review stops
- 21 stops across 5 departments
- Comments issued
- Twice, by Fire Department, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 9, 2024 | Aug 9, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 12, 2024 | Aug 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 12, 2024 | Aug 12, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 12, 2024 | Aug 12, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 12, 2024 | Aug 12, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 14, 2024 | Sep 4, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 19, 2024 | Aug 19, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 21, 2024 | Aug 21, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Aug 23, 2024 | Aug 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2024 | Sep 10, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Sep 10, 2024 | Oct 25, 2024 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Sep 10, 2024 | Dec 19, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 25, 2024 | Oct 25, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 25, 2024 | Oct 28, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 25, 2024 | Nov 1, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 4, 2024 | Dec 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 4, 2024 | Nov 4, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 4, 2024 | Nov 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 4, 2024 | Dec 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 12, 2024 | Dec 17, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2024 | Dec 23, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $7,500
| Name | Role | License on permit |
|---|---|---|
| Anne Marie Cervantes | Architect | C18037 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024