230 Cherry St
San Francisco permit 202408138552 · Presidio Heights
Renovation on all floors. (n) paritial slab on grade. (n) 330sf conditioned space @basement. (n) windows facing street and rear doors, minor siding alterations located at front and rear. 3/f: new bathroom.
- Filed
- Oct 16, 2024
- Issued
- Feb 14, 2025 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 24 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 13, 2024 | Aug 13, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 13, 2024 | Aug 13, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 19, 2024 | Aug 19, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 19, 2024 | Aug 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 19, 2024 | Aug 19, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Sep 25, 2024 | Oct 15, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 1, 2024 | Oct 1, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 3, 2024 | Oct 3, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 4, 2024 | Oct 4, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Oct 15, 2024 | Oct 16, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 16, 2024 | Dec 11, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 16, 2024 | Dec 31, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 16, 2024 | Oct 22, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 16, 2024 | Oct 17, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 16, 2024 | Oct 22, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 16, 2024 | Jan 29, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Dec 16, 2024 | Dec 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 19, 2024 | Jan 27, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 21, 2025 | Jan 21, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 22, 2025 | Jan 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 22, 2025 | Jan 27, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 22, 2025 | Jan 22, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 22, 2025 | Jan 29, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 29, 2025 | Feb 14, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $400,000
| Name | Role | License on permit |
|---|---|---|
| Paul Richard Curren Pavement Engineering Inc. | Architect | C34527 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025