San Francisco permit 202408138552 · Presidio Heights

Home remodelFull plan reviewIssued
Street view · Jan 2025
Google Street View of 230 Cherry St, Jan 2025
Scope of work
As written on the permit application.

Renovation on all floors. (n) paritial slab on grade. (n) 330sf conditioned space @basement. (n) windows facing street and rear doors, minor siding alterations located at front and rear. 3/f: new bathroom.

Timeline
Key dates from the city record.
Filed
Oct 16, 2024
Issued
Feb 14, 2025 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 5 departments
Comments issued
4 times, by Building Inspection
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Aug 13, 2024Administrative

Zoning review

Planning · CP-ZOC

Aug 13, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 19, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 19, 2024Approved

Fire prevention review

Fire Department · SFFD

Aug 19, 2024Administrative

Permit Center

Permit Center · PERMIT-CTR

Oct 15, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Oct 1, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Oct 3, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Oct 4, 2024Not Applicable

Central Permit Bureau

Building Inspection · CPB

Oct 16, 2024Administrative

Building plan review

Building Inspection · BLDG

Dec 11, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Dec 31, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Oct 22, 2024Approved

Zoning review

Planning · CP-ZOC

Oct 17, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 22, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jan 29, 2025Administrative

Building plan review

Building Inspection · BLDG

Dec 16, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jan 27, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Jan 21, 2025Approved

Zoning review

Planning · CP-ZOC

Jan 22, 2025Approved

Building plan review

Building Inspection · BLDG

Jan 27, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jan 22, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 29, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Feb 14, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$400,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Paul Richard Curren

Pavement Engineering Inc.

ArchitectC34527
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202408138552 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record