5 A Presidio Tr
San Francisco permit 202408138563 · Inner Richmond
Detached conversion adu(state program).convert existing detached three car garage to (n)adu via interior remodel,no change in floor area,no change in buildging massing.
- Filed
- Aug 20, 2024
- Issued
- Apr 16, 2025 (8 months after filing)
- Completed
- Apr 6, 2026 (12 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 29 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 9, 2024 | Aug 19, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Aug 16, 2024 | Aug 16, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 16, 2024 | Aug 16, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 16, 2024 | Aug 16, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Aug 19, 2024 | Aug 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 20, 2024 | Aug 22, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 22, 2024 | Feb 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 22, 2024 | Sep 16, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 22, 2024 | Oct 10, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 22, 2024 | Sep 12, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 22, 2024 | Aug 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 22, 2024 | Aug 26, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 22, 2024 | Aug 28, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 22, 2024 | Mar 25, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 23, 2025 | Feb 5, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 23, 2025 | Jan 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 23, 2025 | Jan 24, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 23, 2025 | Jan 27, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 23, 2025 | Jan 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 23, 2025 | Jan 29, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 12, 2025 | Mar 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 12, 2025 | Mar 10, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 12, 2025 | Feb 12, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 12, 2025 | Mar 25, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2025 | Feb 13, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2025 | Feb 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2025 | Feb 12, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Mar 25, 2025 | Mar 25, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 25, 2025 | Apr 16, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Ariel Gessler Ariel Gessler Architects | Architect | C30586 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026