502 14th St
San Francisco permit 202408158748 · Mission
Erect 4-story, type v-a, 2-family residential bldg, r3, no basement
- Filed
- Dec 3, 2024
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 39 stops across 7 departments
- Comments issued
- 9 times, by Permit Center, Building Inspection, Public Utilities, Public Health, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 14, 2024 | Aug 28, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 16, 2024 | Aug 16, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 20, 2024 | Aug 20, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Aug 23, 2024 | Aug 23, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 23, 2024 | Oct 7, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 30, 2024 | Sep 30, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Oct 9, 2024 | Oct 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 9, 2024 | Dec 4, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 4, 2024 | Dec 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 4, 2024 | Dec 10, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 4, 2024 | Dec 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 4, 2024 | Dec 9, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 4, 2024 | Dec 19, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 4, 2024 | In progress | Administrative |
Public Utilities programs review Public Utilities · SFPUC-PRG | Dec 5, 2024 | Dec 6, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 12, 2024 | Dec 12, 2024 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Dec 12, 2024 | Dec 12, 2024 | Approved |
Public health review Public Health · HEALTH | Jan 30, 2025 | Jan 30, 2025 | Administrative |
Public Health HEALTH-MH | Jan 30, 2025 | Jan 30, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 3, 2025 | Feb 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 6, 2025 | Feb 7, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 6, 2025 | Feb 20, 2025 | Issued Comments |
Public Health HEALTH-MH | Feb 7, 2025 | Feb 7, 2025 | Not Applicable |
Public Utilities programs review Public Utilities · SFPUC-PRG | Feb 11, 2025 | Feb 11, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 7, 2025 | Mar 7, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Mar 10, 2025 | Mar 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 3, 2025 | Jun 3, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 5, 2025 | Nov 10, 2025 | Approved |
Public Health HEALTH-MH | Nov 5, 2025 | Nov 5, 2025 | Not Applicable |
Zoning review Planning · CP-ZOC | Nov 5, 2025 | Nov 5, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Nov 10, 2025 | Nov 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 24, 2025 | Nov 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 25, 2025 | Dec 3, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 25, 2025 | Dec 1, 2025 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Dec 4, 2025 | Dec 4, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 4, 2025 | In progress | In Progress |
Urban forestry Public Works · DPW-BUF | Dec 11, 2025 | Dec 16, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Dec 16, 2025 | Dec 16, 2025 | Approved-Stipulated |
Address verification Building Inspection · ADDR | Apr 29, 2026 | Apr 29, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Approved
- Estimated cost
- $1,000,000
| Name | Role | License on permit |
|---|---|---|
| Tom Amedeo Mcelroy Mcelroy Architecture | Architect | C30930 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025