124 Whittier St
San Francisco permit 202408158757 · Excelsior
2nd fl remodel - new bathroom. kitchen remodel to remove wall between kitchen and dining room. new kitchen cabinets
- Filed
- Aug 15, 2024
- Issued
- Sep 19, 2024 (1 month after filing)
- Completed
- Apr 14, 2025 (7 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 6 stops across 2 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 15, 2024 | Aug 15, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 15, 2024 | Aug 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 16, 2024 | Aug 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 20, 2024 | Aug 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 20, 2024 | Aug 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 19, 2024 | Sep 19, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $80,000
| Name | Role | License on permit |
|---|---|---|
| Chong Hong | Engineer | C84784 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022