614 Elizabeth St
San Francisco permit 202408269419 · Noe Valley
Convert 1st fl storage to new foundations, bathroom, bedroom, & family room. 2nd fl- relocate kitchen & bath. revise interior partitions & structural upgrades. 3rd fl- relocate bath. add new bath. revise interior partitions & structural upgrades. new windows at rear. new radiant heating throughtout.
- Filed
- Oct 4, 2024
- Issued
- Apr 29, 2025 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- 6 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 23, 2024 | Sep 12, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 3, 2024 | Sep 3, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 4, 2024 | Sep 4, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Sep 6, 2024 | Sep 6, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 18, 2024 | Oct 3, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 2, 2024 | Oct 2, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2024 | Oct 4, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 4, 2024 | Oct 7, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 4, 2024 | Dec 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 4, 2024 | Oct 25, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 4, 2024 | Oct 21, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 4, 2024 | Oct 8, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 4, 2024 | Apr 2, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 21, 2025 | Feb 21, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 14, 2025 | Mar 14, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 14, 2025 | Mar 17, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 21, 2025 | Mar 21, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 24, 2025 | Mar 31, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 24, 2025 | Mar 26, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 24, 2025 | Mar 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2025 | Mar 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 2, 2025 | Apr 29, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $921,596
| Name | Role | License on permit |
|---|---|---|
| Steven David Stept Feldman Architecture | Architect | C22163 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025