3984 26th St
San Francisco permit 202408279544 · Noe Valley
Kitchen remodel in kind. bathroom remodel, add a bathroom, relocate laundry. move two doors, demo existing chimney, electrical & plumbing work. tile work, sheetrock/taping, flooring & painting. all work to be carried out on the second fl of the building
- Filed
- Aug 27, 2024
- Issued
- Oct 11, 2024 (1 month after filing)
- Completed
- Apr 4, 2025 (6 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 16 stops across 3 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 27, 2024 | Aug 27, 2024 | Administrative |
Intake Building Inspection · INTAKE | Aug 27, 2024 | Aug 27, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Aug 27, 2024 | Aug 27, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 27, 2024 | Aug 27, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 27, 2024 | Aug 27, 2024 | Approved |
Intake Building Inspection · INTAKE | Sep 20, 2024 | Sep 20, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Sep 20, 2024 | Sep 20, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 20, 2024 | Sep 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 20, 2024 | Sep 20, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 20, 2024 | Sep 20, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Oct 11, 2024 | Oct 11, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 11, 2024 | Oct 11, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 11, 2024 | Oct 11, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2024 | Oct 11, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 11, 2024 | Oct 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 11, 2024 | Oct 11, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Ryan G Morris Morris Architecture | Architect | C33359 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025