70 St Marys Av
San Francisco permit 202408299696 · Bernal Heights
Ab1114: horizontal addition to add second residential unit at front of lot. remodel of (e) cottage kitchen, add entry room to cottage. raise portions of roof of (e) cottage. new connecting corridor between residential units.
- Filed
- Sep 25, 2024
- Issued
- Jun 10, 2025 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 42 stops across 6 departments
- Comments issued
- 16 times, by Building Inspection, Public Works, Public Utilities, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 27, 2024 | Sep 17, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 4, 2024 | Sep 4, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 5, 2024 | Sep 5, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 9, 2024 | Sep 9, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Sep 25, 2024 | Sep 25, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 25, 2024 | Sep 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 25, 2024 | Oct 15, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 25, 2024 | Oct 28, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 25, 2024 | Sep 30, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 25, 2024 | Sep 30, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 25, 2024 | Sep 26, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 25, 2024 | May 22, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | Sep 30, 2024 | Oct 28, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 30, 2024 | Sep 30, 2024 | Approved |
Mechanical plan review quality control Building Inspection · MECH-QC | Oct 10, 2024 | Oct 10, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2024 | Oct 11, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 11, 2024 | Oct 21, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 14, 2024 | Oct 14, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 4, 2024 | Dec 4, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 17, 2025 | Jan 17, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Feb 25, 2025 | Mar 3, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 25, 2025 | Mar 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 25, 2025 | Feb 26, 2025 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Feb 25, 2025 | Feb 26, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Feb 25, 2025 | Mar 18, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 25, 2025 | Feb 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 25, 2025 | Mar 3, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 25, 2025 | Feb 26, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 25, 2025 | Mar 25, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 10, 2025 | Apr 16, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 16, 2025 | Apr 17, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 16, 2025 | May 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 16, 2025 | May 20, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 16, 2025 | Apr 22, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 16, 2025 | Apr 17, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 16, 2025 | Apr 22, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 28, 2025 | May 1, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 20, 2025 | May 20, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 20, 2025 | May 20, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 20, 2025 | May 21, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 22, 2025 | May 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 22, 2025 | Jun 10, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $294,511
| Name | Role | License on permit |
|---|---|---|
| Gisela Schmoll Gisela Schmoll Architect Pc | Architect | C-33615 |
| Victor Ramos Ashley & Vance Engineering | Engineer | C86568 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026