34 Roselyn Tr
San Francisco permit 202408299703 · Lone Mountain/USF
Interior remodel and rear deck addition, replace all windows (facing front) add bathroom at 2nd floor, enlarge lower front entry doorway, add sliding glass door at rear, upgrade hvac, water heater, electrical and lighting throughout.
- Filed
- Sep 20, 2024
- Issued
- Jan 27, 2025 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 27 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 29, 2024 | Aug 29, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 29, 2024 | Aug 29, 2024 | Approved |
Intake Building Inspection · INTAKE | Aug 30, 2024 | Aug 30, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 30, 2024 | Aug 30, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 30, 2024 | Aug 30, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 30, 2024 | Aug 30, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 3, 2024 | Sep 19, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 11, 2024 | Sep 11, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 11, 2024 | Sep 11, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 12, 2024 | Sep 12, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Sep 18, 2024 | Sep 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 19, 2024 | Sep 20, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Sep 20, 2024 | Nov 8, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 20, 2024 | Sep 23, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 20, 2024 | Jan 7, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 11, 2024 | Oct 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 2, 2024 | Dec 12, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 2, 2024 | Dec 4, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 2, 2024 | Dec 9, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 2, 2024 | Dec 4, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 2, 2024 | Dec 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 17, 2024 | Dec 20, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 17, 2024 | Dec 19, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 17, 2024 | Dec 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 17, 2024 | Dec 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 17, 2024 | Jan 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 7, 2025 | Jan 27, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $443,000
| Name | Role | License on permit |
|---|---|---|
| Marc Justin Ojanen Ojanen Chiou Architets Llp | Architect | C29102 |
| Chiawang Yeh Chiawang Structural Eng | Engineer | S5164 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2022