2120 Jefferson St
San Francisco permit 202409040006 · Marina
Enclose (e) covered porch at rear yard.provide (n) laundry/mud room.relocate (e) g/f bathroom w/ shower.add kitchen counter/cabinets & bar sink.new hvac & w/h.relocate (e) elec pnl.relocate (e) r-yard gate.reconfigure (e) 2 car garage.replace (e) garage doors & windows.
- Filed
- Sep 20, 2024
- Issued
- Jan 14, 2025 (4 months after filing)
- Completed
- Jan 20, 2026 (12 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 20 stops across 5 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 30, 2024 | Sep 17, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 10, 2024 | Sep 10, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 11, 2024 | Sep 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2024 | Sep 23, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 23, 2024 | Sep 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 23, 2024 | Nov 13, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 23, 2024 | Oct 4, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 23, 2024 | Sep 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 23, 2024 | Sep 26, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 23, 2024 | Jan 3, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 10, 2024 | Oct 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 10, 2024 | Oct 15, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 10, 2024 | Oct 21, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 10, 2024 | Oct 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 10, 2024 | Dec 16, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 10, 2024 | Dec 18, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 10, 2024 | Dec 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 10, 2024 | Dec 17, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 10, 2024 | Jan 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 3, 2025 | Jan 14, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $412,000
| Name | Role | License on permit |
|---|---|---|
| Jay Sherlock Studio J. Architecture | Architect | C-33354 |
| Seri Ngernwattana Seri Ngerwattana, Pe | Engineer | C-66949 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2008