88 Spear St
San Francisco permit 202409040025 · Financial District/South Beach
Retail and office renovation to (e) bldg. levels b, 1, 2 core, shell and interior amenities renovation. separation of north and south side of lvl 1 w/1-hr rated construction. construction of inter story feature stairs in basement to lvl 1, and lvl 1 to lvl 2. demo (e) restrooms and construct (n)....
- Filed
- Sep 4, 2024
- Issued
- Jun 26, 2025 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 62 stops across 7 departments
- Comments issued
- 20 times, by Building Inspection, Planning, Fire Department, Public Works, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 30, 2024 | Sep 17, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 6, 2024 | Sep 6, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Sep 10, 2024 | Sep 10, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 11, 2024 | Sep 11, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 13, 2024 | Sep 13, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 16, 2024 | Sep 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2024 | Sep 24, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 24, 2024 | Sep 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 24, 2024 | Nov 6, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 24, 2024 | Oct 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 24, 2024 | Jan 9, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 24, 2024 | Sep 25, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Sep 24, 2024 | Oct 17, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 24, 2024 | Sep 27, 2024 | Approved |
Public health review Public Health · HEALTH | Sep 24, 2024 | Sep 24, 2024 | Administrative |
Public Health HEALTH-MH | Sep 24, 2024 | Sep 25, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 24, 2024 | Jun 13, 2025 | Administrative |
Public Health HEALTH-HM | Sep 27, 2024 | Sep 30, 2024 | Approved |
Public health food review Public Health · HEALTH-FD | Oct 2, 2024 | Oct 9, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 28, 2024 | Jan 14, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 4, 2024 | Nov 4, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 5, 2024 | Nov 6, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 5, 2024 | Dec 6, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 5, 2024 | Dec 26, 2024 | Approved |
Public Health HEALTH-MH | Dec 5, 2024 | Jan 21, 2025 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Dec 5, 2024 | Dec 12, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2024 | Dec 10, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 5, 2024 | Dec 26, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 5, 2024 | Dec 12, 2024 | Approved |
Public Health HEALTH-HM | Dec 5, 2024 | Dec 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 6, 2024 | Jan 3, 2025 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Feb 11, 2025 | Feb 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 11, 2025 | Feb 24, 2025 | Approved |
Public Health HEALTH-MH | Feb 14, 2025 | Feb 14, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Feb 18, 2025 | Feb 27, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 19, 2025 | Feb 19, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 21, 2025 | Feb 21, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 14, 2025 | Mar 14, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 14, 2025 | Mar 14, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 17, 2025 | Apr 17, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 29, 2025 | Apr 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 6, 2025 | May 23, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 6, 2025 | May 14, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | May 6, 2025 | May 6, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 13, 2025 | May 13, 2025 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | May 13, 2025 | May 13, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 14, 2025 | May 16, 2025 | Approved |
Public Health HEALTH-MH | May 14, 2025 | May 14, 2025 | Not Applicable |
Structural plan approval Building Inspection · PAD-STR | May 20, 2025 | May 20, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 23, 2025 | May 30, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 23, 2025 | May 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 30, 2025 | May 30, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 30, 2025 | May 30, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 30, 2025 | May 30, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 30, 2025 | Jun 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 30, 2025 | May 30, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 30, 2025 | Jun 10, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | May 30, 2025 | May 30, 2025 | Approved-Stipulated |
Public Health HEALTH-HM | May 30, 2025 | May 30, 2025 | Approved |
Public Health HEALTH-MH | May 30, 2025 | May 30, 2025 | Not Applicable |
Urban forestry Public Works · DPW-BUF | Jun 9, 2025 | Jun 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2025 | Jun 26, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $5,500,000
| Name | Role | License on permit |
|---|---|---|
| Guion Cabell Childress Otj Architects | Architect | C39053 |
| Jordan Elling Hague Dci Engineers | Engineer | S6509 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026