2519 Pacific Av
San Francisco permit 202409050083 · Pacific Heights
To comply with nov #202291403: construction of a new cast-in-place concrete retaining wall with hand dug pier foundations cast against the (e) damaged concrete retaining wall at back of property line 13'-6" high x 47'-6'' long between adjacent property lines.
- Filed
- Oct 14, 2024
- Issued
- Mar 19, 2025 (5 months after filing)
- Completed
- Aug 28, 2025 (5 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 17 stops across 3 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 5, 2024 | Sep 5, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 5, 2024 | Sep 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 5, 2024 | Sep 5, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Sep 11, 2024 | Sep 27, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 16, 2024 | Sep 16, 2024 | Not Applicable |
Code enforcement Building Inspection · CES | Sep 18, 2024 | Sep 18, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 19, 2024 | Sep 19, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 20, 2024 | Sep 20, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Sep 26, 2024 | Sep 26, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 27, 2024 | Oct 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 18, 2024 | Oct 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 18, 2024 | Nov 22, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 18, 2024 | Mar 12, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 24, 2025 | Feb 3, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 24, 2025 | Mar 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 20, 2025 | Feb 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 12, 2025 | Mar 19, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Eugene Yu-Ming Tuan Tuan & Robinson Str. Engineer | Engineer | S3982 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022