1437 Mason St
San Francisco permit 202409050181 · Nob Hill
Facade improvements, full interior remodel, remove rear stair, replace front stair w/in (e) envelope, (n) foundation interior conversion of basement, all work w/in (e) envelope.
- Filed
- Jun 30, 2025
- Issued
- Feb 25, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 32 stops across 5 departments
- Comments issued
- 10 times, by Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 5, 2024 | Sep 5, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 16, 2024 | Dec 16, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 26, 2025 | Feb 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 7, 2025 | Mar 7, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Mar 27, 2025 | Mar 27, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 28, 2025 | Mar 28, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | May 15, 2025 | Jun 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 9, 2025 | Jun 30, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 9, 2025 | Jun 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 9, 2025 | Jul 25, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 9, 2025 | Jul 25, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 9, 2025 | Jul 14, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 9, 2025 | Jun 12, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 9, 2025 | Jun 18, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jun 9, 2025 | Feb 20, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jul 31, 2025 | Aug 6, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 5, 2025 | Nov 6, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 6, 2025 | Nov 6, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 13, 2025 | Nov 13, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 14, 2025 | Nov 14, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 14, 2025 | Nov 14, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 7, 2026 | Jan 7, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 7, 2026 | Jan 7, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 22, 2026 | Jan 22, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 30, 2026 | Jan 30, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 3, 2026 | Feb 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 3, 2026 | Feb 9, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 3, 2026 | Feb 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 3, 2026 | Feb 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 3, 2026 | Feb 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 3, 2026 | Feb 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 20, 2026 | Feb 25, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $467,000
| Name | Role | License on permit |
|---|---|---|
| Michael William Terndrup Eag Studio Architecture | Architect | C40160 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025