4365 23rd St
San Francisco permit 202409060254 · Noe Valley
Create new adu in basement ord. 162-16 ab1114. infill (e) lightwell. relocate (e) stair from street level to upper floor to connect to main house. create new stair from street level to new basement adu. earth shoring is required under a separate permit.
- Filed
- Oct 15, 2024
- Issued
- Sep 2, 2025 (11 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 44 stops across 6 departments
- Comments issued
- 16 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 4, 2024 | Sep 16, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 12, 2024 | Sep 12, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 12, 2024 | Sep 12, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 13, 2024 | Sep 13, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 19, 2024 | Sep 30, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 23, 2024 | Sep 23, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 27, 2024 | Sep 27, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 30, 2024 | Sep 30, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 30, 2024 | Sep 30, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 30, 2024 | Oct 15, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 15, 2024 | Aug 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 15, 2024 | Nov 4, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 15, 2024 | Dec 18, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 15, 2024 | Oct 23, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 15, 2024 | Oct 29, 2024 | Not Applicable |
Fire prevention review Fire Department · SFFD | Oct 15, 2024 | Oct 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 15, 2024 | Oct 16, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 15, 2024 | Oct 16, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 15, 2024 | Oct 23, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 15, 2024 | Aug 12, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 24, 2024 | Oct 24, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 29, 2024 | Oct 29, 2024 | Issued Comments |
Mechanical plan review quality control Building Inspection · MECH-QC | Oct 29, 2024 | Oct 29, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 30, 2024 | Oct 30, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 25, 2024 | Nov 25, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 11, 2025 | Feb 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2025 | Feb 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 19, 2025 | Feb 20, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 7, 2025 | Mar 21, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 27, 2025 | Apr 7, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 28, 2025 | Apr 30, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 8, 2025 | Apr 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2025 | Apr 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 22, 2025 | May 1, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 12, 2025 | Jun 12, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 12, 2025 | Jun 18, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 12, 2025 | Aug 5, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 12, 2025 | Jun 13, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 18, 2025 | Jun 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2025 | Jul 1, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 17, 2025 | Jul 17, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 7, 2025 | Aug 7, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Aug 11, 2025 | Aug 12, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 12, 2025 | Sep 2, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $985,714
| Name | Role | License on permit |
|---|---|---|
| James Howard Westover Wda William Duff Architects | Architect | C21728 |
| Jillian Van Enckevort Ftf Engineering | Engineer | S-5394 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022