110 Alpine Tr
San Francisco permit 202409090325 · Castro/Upper Market
To erect 1 story, type v-b, detach garage.
- Filed
- Oct 31, 2024
- Issued
- Aug 21, 2025 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 48 stops across 6 departments
- Comments issued
- 12 times, by Permit Center, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 4, 2024 | Sep 16, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Sep 9, 2024 | Nov 1, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 13, 2024 | Sep 13, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 16, 2024 | Sep 16, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Sep 17, 2024 | Sep 17, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 1, 2024 | Nov 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 1, 2024 | Nov 22, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 1, 2024 | Dec 4, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 1, 2024 | Nov 5, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 1, 2024 | Nov 14, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 1, 2024 | Nov 1, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 1, 2024 | Aug 8, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 21, 2025 | Jan 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 21, 2025 | Feb 3, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 21, 2025 | Jan 30, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 21, 2025 | Jan 29, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2025 | Jan 24, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 21, 2025 | Jan 27, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 28, 2025 | Apr 21, 2025 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Feb 26, 2025 | Feb 28, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 26, 2025 | Feb 27, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 26, 2025 | Feb 27, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 26, 2025 | Mar 4, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 26, 2025 | Feb 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 26, 2025 | Mar 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 24, 2025 | Mar 27, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 24, 2025 | Apr 2, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 24, 2025 | Mar 25, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 24, 2025 | Mar 27, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 24, 2025 | Mar 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2025 | Mar 26, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 23, 2025 | Apr 24, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 23, 2025 | Apr 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 23, 2025 | Apr 25, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 23, 2025 | Jun 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 23, 2025 | Apr 28, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 23, 2025 | Apr 30, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 23, 2025 | Apr 25, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 14, 2025 | Jul 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 14, 2025 | Jul 16, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 14, 2025 | Jul 21, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 14, 2025 | Jul 15, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jul 14, 2025 | Jul 16, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 14, 2025 | Aug 7, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jul 14, 2025 | Jul 15, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 15, 2025 | Jul 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 15, 2025 | Jul 16, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Aug 8, 2025 | Aug 21, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Reinstated
- Estimated cost
- $142,023
| Name | Role | License on permit |
|---|---|---|
| Michael James Hennessey Michael Hennessey Architecture | Architect | C31229 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025