Rebuild (e) retaining wall using steel beam, match (e) look.

Timeline
Key dates from the city record.
Filed
Oct 31, 2024
Issued
Jan 23, 2025 (3 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 5 departments
Comments issued
3 times, by Building Inspection
Review stopFinishedResult

Apartment and hotel inspection

Building Inspection · HIS

Sep 10, 2024Administrative

Intake

Building Inspection · INTAKE

Sep 10, 2024Administrative

Zoning review

Planning · CP-ZOC

Sep 10, 2024Approved

Intake

Building Inspection · INTAKE

Sep 24, 2024Administrative

Zoning review

Planning · CP-ZOC

Sep 24, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Sep 24, 2024Administrative

Permit Center

Permit Center · PERMIT-CTR

Oct 28, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Sep 27, 2024Administrative

Building pre-screening

Building Inspection · PRE-BLDG

Oct 7, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Oct 15, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Oct 31, 2024Administrative

Structural plan approval

Building Inspection · PAD-STR

Nov 18, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 5, 2024Not Applicable

Street use and mapping

Public Works · DPW-BSM

Nov 8, 2024Approved

Permit Processing Center

Building Inspection · PPC

Dec 13, 2024Administrative

Structural plan approval

Building Inspection · PAD-STR

Dec 9, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Nov 26, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Dec 3, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Dec 11, 2024Approved

Zoning review

Planning · CP-ZOC

Dec 12, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Dec 11, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jan 23, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Cancelled
Estimated cost
$125,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Anoush Zebarjadian

Cse Structural Engineers

EngineerS-3313
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202409100466 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record