2225 23rd St
San Francisco permit 202409100466 · Potrero Hill
Rebuild (e) retaining wall using steel beam, match (e) look.
- Filed
- Oct 31, 2024
- Issued
- Jan 23, 2025 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Sep 10, 2024 | Sep 10, 2024 | Administrative |
Intake Building Inspection · INTAKE | Sep 10, 2024 | Sep 10, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 10, 2024 | Sep 10, 2024 | Approved |
Intake Building Inspection · INTAKE | Sep 24, 2024 | Sep 24, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 24, 2024 | Sep 24, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 24, 2024 | Sep 24, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Sep 27, 2024 | Oct 28, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 27, 2024 | Sep 27, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Oct 7, 2024 | Oct 7, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Oct 15, 2024 | Oct 15, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 31, 2024 | Oct 31, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Oct 31, 2024 | Nov 18, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 31, 2024 | Nov 5, 2024 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Oct 31, 2024 | Nov 8, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 31, 2024 | Dec 13, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Nov 26, 2024 | Dec 9, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 26, 2024 | Nov 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 26, 2024 | Dec 3, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 11, 2024 | Dec 11, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 11, 2024 | Dec 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 11, 2024 | Dec 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 13, 2024 | Jan 23, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $125,000
| Name | Role | License on permit |
|---|---|---|
| Anoush Zebarjadian Cse Structural Engineers | Engineer | S-3313 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2022