3911 V 03rd St
San Francisco permit 202409110518 · Bayview Hunters Point
Install 3 delta 350 kw hp chargers and cabinets. install 3 charging equip skids and foundatoins. install evgo provided signage. install switchgear assemble and all underground conduit and conductors. perform all civil work required for chargers. restripe parking stalls.
- Filed
- Dec 30, 2024
- Issued
- Feb 14, 2025 (2 months after filing)
- Completed
- Jul 29, 2025 (5 months after issuance)
- Review stops
- 21 stops across 4 departments
- Comments issued
- 6 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 11, 2024 | Sep 11, 2024 | Administrative |
Intake Building Inspection · INTAKE | Sep 13, 2024 | Sep 13, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 13, 2024 | Sep 13, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 8, 2024 | Nov 8, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 8, 2024 | Nov 8, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Nov 11, 2024 | Nov 21, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 15, 2024 | Nov 15, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 12, 2024 | Dec 24, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Dec 24, 2024 | Dec 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 26, 2024 | Dec 30, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Dec 30, 2024 | Jan 8, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 30, 2024 | Jan 3, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 30, 2024 | Feb 12, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | Jan 21, 2025 | Jan 21, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 23, 2025 | Jan 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 23, 2025 | Jan 24, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 23, 2025 | Jan 23, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 23, 2025 | Feb 5, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 31, 2025 | Feb 5, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 11, 2025 | Feb 11, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 12, 2025 | Feb 14, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $40,000
| Name | Role | License on permit |
|---|---|---|
| Stanislav Gorbis Blymyer | Architect | C81928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024