330 Linden St
San Francisco permit 202409160834 · Hayes Valley
Installation of (n) storefront opening entry & egress doors on linden st side of 425-427 hayes st throughout building. (n) interior ramp to provide ada compliance structural scope includes storefront opening interior steps. (n) slab on grade & columns. existing sam flores mural on linden st
- Filed
- Sep 16, 2024
- Issued
- Feb 27, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 16 stops across 3 departments
- Comments issued
- 7 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Plumbing inspector Building Inspection · PID-INSP | Sep 16, 2024 | Sep 16, 2024 | Approved |
Intake Building Inspection · INTAKE | Sep 16, 2024 | Sep 16, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 18, 2024 | Sep 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 18, 2024 | Sep 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 24, 2024 | Sep 24, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 24, 2024 | Sep 24, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 30, 2024 | Sep 30, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 30, 2024 | Sep 30, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 8, 2024 | Oct 8, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2024 | Oct 23, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 24, 2024 | Oct 24, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 24, 2024 | Oct 24, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 29, 2024 | Oct 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 11, 2024 | Dec 11, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 12, 2024 | Dec 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 27, 2025 | Feb 27, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $470,000
| Name | Role | License on permit |
|---|---|---|
| Douglas John Burnham Envelope A+D | Architect | C25383 |
| Nate Williams Mosswood Engineering | Engineer | C62068 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026