2025 Van Ness Av
San Francisco permit 202409181064 · Pacific Heights
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Structural revision to 202311130657: revision to architectural equipment, lighting, revising demo work. revision to structural framing of roof unit, show new stepped concrete, remove detail where new footing on north wall (new footing is built under wall). revise shoring post due to damaged sill pl
- Filed
- Oct 9, 2024
- Issued
- Feb 18, 2025 (4 months after filing)
- Completed
- Oct 7, 2025 (8 months after issuance)
- Review stops
- 21 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 18, 2024 | Sep 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 19, 2024 | Sep 19, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 19, 2024 | Oct 9, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 23, 2024 | Sep 23, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 23, 2024 | Sep 23, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 23, 2024 | Sep 23, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 27, 2024 | Sep 27, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Oct 9, 2024 | Oct 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 9, 2024 | Oct 9, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 9, 2024 | Oct 9, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Oct 9, 2024 | Dec 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 9, 2024 | Oct 30, 2024 | Not Applicable |
Fire prevention review Fire Department · SFFD | Oct 9, 2024 | Nov 15, 2024 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Oct 9, 2024 | Oct 22, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 9, 2024 | Oct 21, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 9, 2024 | Feb 11, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jan 24, 2025 | Jan 28, 2025 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Jan 24, 2025 | Feb 3, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2025 | Feb 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 11, 2025 | Feb 11, 2025 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Feb 11, 2025 | Feb 18, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Shawn M Anderson Msa Architecture | Architect | C31273 |
| Ramon Gilsanz Gilsanz Murray Steficek Llp | Engineer | S4161 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019