San Francisco permit 202409181084 · Noe Valley

Seismic retrofit or foundationFull plan reviewIssued
Street view · Dec 2014
Google Street View of 707 Douglass St, Dec 2014
Scope of work
As written on the permit application.

Foundation replacement; new interior stair; remodel 2 bathrooms; new platform at grade; convert laundry to shop. no exterior alterations

Timeline
Key dates from the city record.
Filed
Oct 21, 2024
Issued
Mar 27, 2025 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 5 departments
Comments issued
6 times, by Building Inspection
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Sep 18, 2024Administrative

Zoning review

Planning · CP-ZOC

Sep 18, 2024Not Applicable

Fire prevention review

Fire Department · SFFD

Sep 18, 2024Not Applicable

Permit Center

Permit Center · PERMIT-CTR

Oct 18, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Oct 10, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Oct 16, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Oct 22, 2024Administrative

Building plan review

Building Inspection · BLDG

Feb 4, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jan 9, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 5, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

Oct 31, 2024Not Applicable

Public Utilities Commission review

Public Utilities · SFPUC

Oct 24, 2024Approved

Permit Processing Center

Building Inspection · PPC

Mar 19, 2025Administrative

Mechanical plan review quality control

Building Inspection · MECH-QC

Nov 19, 2024Administrative

Building plan review

Building Inspection · BLDG

Feb 21, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Feb 18, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 24, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 5, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 3, 2025Approved

Building plan review

Building Inspection · BLDG

Mar 5, 2025Issued Comments

Building plan review quality control

Building Inspection · BLDG-QC

Mar 5, 2025Administrative

Building plan review

Building Inspection · BLDG

Mar 6, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Mar 17, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 12, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 12, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Mar 27, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$387,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Craig Thomas O'connell

Craig O'connell Architect

ArchitectC-31771
Lisa Wai Sum Tse

Integrand Structural Engineer

Engineer4839
Sources