707 Douglass St
San Francisco permit 202409181084 · Noe Valley
Foundation replacement; new interior stair; remodel 2 bathrooms; new platform at grade; convert laundry to shop. no exterior alterations
- Filed
- Oct 21, 2024
- Issued
- Mar 27, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 26 stops across 5 departments
- Comments issued
- 6 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 18, 2024 | Sep 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 18, 2024 | Sep 18, 2024 | Not Applicable |
Fire prevention review Fire Department · SFFD | Sep 18, 2024 | Sep 18, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Oct 3, 2024 | Oct 18, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 10, 2024 | Oct 10, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 16, 2024 | Oct 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 22, 2024 | Oct 22, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 22, 2024 | Feb 4, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 22, 2024 | Jan 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 22, 2024 | Dec 5, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 22, 2024 | Oct 31, 2024 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Oct 22, 2024 | Oct 24, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 22, 2024 | Mar 19, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Nov 19, 2024 | Nov 19, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 12, 2025 | Feb 21, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 18, 2025 | Feb 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 24, 2025 | Feb 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 25, 2025 | Mar 5, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 3, 2025 | Mar 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 4, 2025 | Mar 5, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Mar 5, 2025 | Mar 5, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 6, 2025 | Mar 6, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 6, 2025 | Mar 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 6, 2025 | Mar 12, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 6, 2025 | Mar 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 19, 2025 | Mar 27, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $387,000
| Name | Role | License on permit |
|---|---|---|
| Craig Thomas O'connell Craig O'connell Architect | Architect | C-31771 |
| Lisa Wai Sum Tse Integrand Structural Engineer | Engineer | 4839 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2014