25 Van Ness Av
San Francisco permit 202409191147 · Hayes Valley
Project consists exclusively of elevator modernization of two traction elevators (elevators #1 and #2) and one hydraulic elevator (#3) at 25 van ness ave
- Filed
- Sep 19, 2024
- Issued
- Sep 8, 2025 (12 months after filing)
- Completed
- Not completed yet
- Review stops
- 18 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 19, 2024 | Sep 19, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Sep 19, 2024 | Sep 19, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 19, 2024 | Sep 19, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 19, 2024 | Sep 19, 2024 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Sep 19, 2024 | Sep 19, 2024 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Oct 15, 2024 | Oct 15, 2024 | Approved |
Intake Building Inspection · INTAKE | Oct 17, 2024 | Oct 17, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 17, 2024 | Oct 17, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 17, 2024 | Oct 17, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 17, 2024 | Oct 17, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 17, 2024 | Oct 17, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 17, 2024 | Oct 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 21, 2024 | Oct 21, 2024 | Approved |
Intake Building Inspection · INTAKE | Oct 31, 2024 | Oct 31, 2024 | Administrative |
Intake Building Inspection · INTAKE | Feb 6, 2025 | Feb 6, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | Feb 6, 2025 | Feb 6, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 6, 2025 | Feb 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 8, 2025 | Sep 8, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $1,500,000
| Name | Role | License on permit |
|---|---|---|
| Paul I Cooper Tef Design | Architect | C28490 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026