65 Aerial Wy
San Francisco permit 202409191152 · Inner Sunset
Alter site permit 202209082081-s: interior remodel at 1/f - remove service stair, remove garage post, install new beam. interior remodel at 2/f - remodel kitchen and 2 bathrooms, fill in service stair flr opening and service stair door opening. other - replace all windows in (e) rough openings.
- Filed
- Oct 4, 2024
- Issued
- Feb 11, 2025 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 43 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Public Utilities, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 17, 2024 | Oct 3, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 20, 2024 | Sep 20, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 23, 2024 | Sep 23, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 26, 2024 | Sep 26, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2024 | Oct 7, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 7, 2024 | Oct 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 7, 2024 | Nov 1, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 7, 2024 | Oct 17, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 7, 2024 | Oct 17, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 7, 2024 | Feb 4, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Oct 21, 2024 | Oct 21, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 26, 2024 | Nov 26, 2024 | Not Applicable |
Zoning review Planning · CP-ZOC | Dec 13, 2024 | Jan 13, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 13, 2024 | Dec 20, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 13, 2024 | Dec 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 16, 2024 | Dec 16, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 16, 2025 | Jan 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 16, 2025 | Jan 16, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 16, 2025 | Jan 28, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jan 16, 2025 | Jan 28, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 4, 2025 | Feb 11, 2025 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 24, 2025 | May 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 15, 2025 | May 15, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 15, 2025 | May 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 15, 2025 | Jun 29, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 15, 2025 | Jun 29, 2025 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | May 15, 2025 | Jul 2, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 15, 2025 | May 22, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 15, 2025 | May 27, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | May 15, 2025 | Jul 9, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 15, 2025 | May 21, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 15, 2025 | Aug 20, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jun 3, 2025 | Jun 4, 2025 | Approved |
Mechanical plan review quality control Building Inspection · MECH-QC | Jul 2, 2025 | Jul 2, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 11, 2025 | Jul 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 11, 2025 | Jul 22, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 11, 2025 | Jul 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 11, 2025 | Jul 16, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 11, 2025 | Jul 15, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 11, 2025 | Jul 14, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 11, 2025 | Jul 15, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 5, 2025 | Aug 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 20, 2025 | Aug 22, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $24,982
| Name | Role | License on permit |
|---|---|---|
| Edward Lee Hammack Edw. Lee Hammack, Architect | Architect | C13890 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019