641 Baker St

San Francisco permit 202409201249 · Lone Mountain/USF

Home remodelFull plan reviewComplete
Street view · Mar 2022
Google Street View of 641 Baker St, Mar 2022
Scope of work
As written on the permit application.

Interior remodel of 3rd level of existing building.

Timeline
Key dates from the city record.
Filed
Dec 2, 2024
Issued
Aug 27, 2025 (9 months after filing)
Completed
Jul 23, 2026 (11 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
27 stops across 5 departments
Comments issued
10 times, by Permit Center, Building Inspection, Public Utilities
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Sep 20, 2024Administrative

Zoning review

Planning · CP-ZOC

Sep 20, 2024Approved

Permit Center

Permit Center · PERMIT-CTR

Oct 15, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Oct 7, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Oct 9, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Nov 18, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Nov 8, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Nov 15, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Nov 18, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Dec 3, 2024Administrative

Zoning review

Planning · CP-ZOC

Jan 22, 2025Approved

Building plan review

Building Inspection · BLDG

Jan 21, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 19, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Dec 4, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 17, 2024Approved

Permit Processing Center

Building Inspection · PPC

Aug 8, 2025Administrative

Building plan review

Building Inspection · BLDG

May 28, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 4, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jul 10, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 10, 2025Approved

Zoning review

Planning · CP-ZOC

Aug 8, 2025Not Applicable

Building plan review

Building Inspection · BLDG

Jul 28, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 28, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jul 30, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 5, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 7, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Aug 27, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$150,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Rex Stuart Mclean

Rex Mclean Architect

ArchitectC-14477
Steven Kirk Barg

Steve Barg Structural Designs

EngineerS5983
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202409201249 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record