495 Ralston St

San Francisco permit 202409251624 · Oceanview/Merced/Ingleside

Home remodelFull plan reviewComplete
Street view · Apr 2011
Google Street View of 495 Ralston St, Apr 2011
Scope of work
As written on the permit application.

Interior renovation of (e) sfd, demo and repair of garage slab and creation of a new bahtroom @ basement lvl, 2 new window openings @ garage lvl, and a new folding door system opening (12'in length) @ great room. all new windows in (e) openings.

Timeline
Key dates from the city record.
Filed
Nov 6, 2024
Issued
Feb 4, 2025 (3 months after filing)
Completed
Jul 7, 2025 (5 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
34 stops across 4 departments
Comments issued
8 times, by Permit Center, Building Inspection
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Oct 9, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Sep 27, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Oct 1, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Oct 4, 2024Not Applicable

Permit Center

Permit Center · PERMIT-CTR

Nov 4, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Oct 25, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Nov 1, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Nov 6, 2024Administrative

Zoning review

Planning · CP-ZOC

Nov 15, 2024Approved

Building plan review

Building Inspection · BLDG

Dec 12, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 20, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Nov 13, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jan 31, 2025Administrative

Mechanical and energy plan review

Building Inspection · MECH

Dec 16, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Dec 9, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 12, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 26, 2024Approved

Zoning review

Planning · CP-ZOC

Dec 19, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 20, 2024Approved

Building plan review

Building Inspection · BLDG

Dec 26, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Jan 8, 2025Approved

Building plan review

Building Inspection · BLDG

Jan 6, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 14, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 8, 2025Approved

Building plan review

Building Inspection · BLDG

Jan 23, 2025Administrative

Zoning review

Planning · CP-ZOC

Jan 21, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 14, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jan 21, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 28, 2025Approved

Zoning review

Planning · CP-ZOC

Jan 21, 2025Approved

Building plan review

Building Inspection · BLDG

Jan 27, 2025Approved

Zoning review

Planning · CP-ZOC

Jan 29, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jan 28, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Feb 4, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$75,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
David A Kesler

David Kesler Architect

ArchitectC28122
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202409251624 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record