38 Hotaling Pl #0
San Francisco permit 202409261671 · Chinatown
1st & basement fl ti partial demo of (e) 1st fl plate for new openings. remove 2 existing stairs and replace with (n) accessible stairs. add (n) accessible bathroom, storage & mech storgae in the basement. add (n) wet bar & kitchen at 1st fl. remodel (e) bathroom at 1st fl
- Filed
- Nov 4, 2024
- Issued
- Mar 6, 2025 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 32 stops across 5 departments
- Comments issued
- 9 times, by Permit Center, Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 26, 2024 | Oct 15, 2024 | Issued Comments |
Intake Building Inspection · INTAKE | Sep 26, 2024 | Sep 26, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 26, 2024 | Sep 26, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 4, 2024 | Oct 4, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Oct 9, 2024 | Oct 9, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 10, 2024 | Oct 10, 2024 | Not Applicable |
Zoning review Planning · CP-ZOC | Oct 15, 2024 | Nov 5, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Oct 22, 2024 | Nov 1, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 31, 2024 | Oct 31, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 1, 2024 | Nov 1, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 4, 2024 | Nov 5, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 5, 2024 | Dec 9, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 5, 2024 | Jan 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 5, 2024 | Nov 22, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 5, 2024 | Nov 26, 2024 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Nov 5, 2024 | Nov 8, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 5, 2024 | Mar 4, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Dec 2, 2024 | Dec 2, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jan 24, 2025 | Feb 3, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 24, 2025 | Jan 28, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 24, 2025 | Jan 27, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2025 | Jan 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 10, 2025 | Feb 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 10, 2025 | Feb 18, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 10, 2025 | Feb 13, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2025 | Feb 24, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 10, 2025 | Feb 26, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 21, 2025 | Feb 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 21, 2025 | Feb 27, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 21, 2025 | Feb 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 25, 2025 | Feb 25, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 4, 2025 | Mar 6, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $156,130
| Name | Role | License on permit |
|---|---|---|
| Maurice Lombardo Taylor Lombardo Architects | Architect | C26362 |
| Peter Enjing Yu Structus | Engineer | S4447 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2018