125 Stanyan St

San Francisco permit 202409261696 · Lone Mountain/USF

Home remodel (type unconfirmed)Full plan reviewIssued
Street view · Sep 2026
Google Street View of 125 Stanyan St, Sep 2026
Scope of work
As written on the permit application.

1/f: add (1)living room, (1)bedroom, (1)bath and (1)office, add wall to seaparate garage and new living space, add washer & dryer, add (1)new heat-pump fau for 1/f use. 2/f: incorporate atrium into living space, removing wall between kitchen and atrium and side room, add (1)bath, kitchen & (e) bath.

Timeline
Key dates from the city record.
Filed
Dec 1, 2024
Issued
Jul 1, 2025 (7 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
51 stops across 6 departments
Comments issued
9 times, by Permit Center, Building Inspection, Public Utilities, Planning, Fire Department
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Oct 18, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Oct 16, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Oct 16, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Oct 18, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Nov 6, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Nov 4, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Nov 6, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Dec 2, 2024Administrative

Zoning review

Planning · CP-ZOC

Dec 3, 2024Approved

Building plan review

Building Inspection · BLDG

Jan 24, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 26, 2025Approved

Fire prevention review

Fire Department · SFFD

Dec 4, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 17, 2024Issued Comments

Public health review

Public Health · HEALTH

Dec 2, 2024Administrative

Public Health

HEALTH-MH

Dec 2, 2024Not Applicable

Permit Processing Center

Building Inspection · PPC

Jun 16, 2025Administrative

Zoning review

Planning · CP-ZOC

Dec 16, 2024Approved

Fire prevention review

Fire Department · SFFD

Dec 31, 2024Approved

Mechanical plan review quality control

Building Inspection · MECH-QC

Dec 19, 2024Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Dec 19, 2024Approved

Zoning review

Planning · CP-ZOC

Dec 26, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 7, 2025Approved

Fire prevention review

Fire Department · SFFD

Jan 23, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 3, 2025Approved

Zoning review

Planning · CP-ZOC

Jan 24, 2025Approved

Building plan review

Building Inspection · BLDG

Mar 17, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Feb 18, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 19, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 20, 2025Approved

Zoning review

Planning · CP-ZOC

Feb 26, 2025Approved

Fire prevention review

Fire Department · SFFD

Feb 25, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 27, 2025Approved

Building plan review

Building Inspection · BLDG

Apr 8, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Mar 18, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 8, 2025Approved

Fire prevention review

Fire Department · SFFD

Mar 19, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 20, 2025Approved

Fire prevention review

Fire Department · SFFD

Apr 2, 2025Approved

Zoning review

Planning · CP-ZOC

Apr 2, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 7, 2025Approved

Zoning review

Planning · CP-ZOC

Apr 15, 2025Approved

Building plan review

Building Inspection · BLDG

Apr 22, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 16, 2025Approved

Fire prevention review

Fire Department · SFFD

Apr 24, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 23, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 5, 2025Approved

Zoning review

Planning · CP-ZOC

Jun 2, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 4, 2025Approved

Fire prevention review

Fire Department · SFFD

Jun 2, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 10, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 1, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$305,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Hongbo Yang

W.H. Consultant Inc.

EngineerC88467
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202409261696 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record