235 Capitol Av
San Francisco permit 202409271847 · Oceanview/Merced/Ingleside
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Prop h: first time tenant improvement for new house cleaning business in existing shell building. replace front facade windows with fiberglass. mep work deferred. structural work associated with tenant improvement. ref pa# 201204259123, to be finaled prior or simultanious.
- Filed
- Oct 10, 2024
- Issued
- Dec 18, 2024 (2 months after filing)
- Completed
- Not completed yet
- Review stops
- 39 stops across 5 departments
- Comments issued
- 9 times, by Planning, Fire Department, Public Works, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Aug 30, 2024 | Aug 30, 2024 | Approved |
Electrical inspector Building Inspection · EID-INSP | Aug 30, 2024 | Aug 30, 2024 | Approved |
Plumbing inspector Building Inspection · PID-INSP | Aug 30, 2024 | Aug 30, 2024 | Approved |
Building inspector Building Inspection · BID-INSP | Sep 27, 2024 | Sep 27, 2024 | Approved |
Intake Building Inspection · INTAKE | Sep 27, 2024 | Sep 27, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 27, 2024 | Sep 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 27, 2024 | Sep 27, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 1, 2024 | Oct 1, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 1, 2024 | Oct 1, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 1, 2024 | Oct 1, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 1, 2024 | Oct 1, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 1, 2024 | Oct 1, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 1, 2024 | Oct 1, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 7, 2024 | Oct 10, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 10, 2024 | Oct 10, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 10, 2024 | Oct 10, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 10, 2024 | Dec 13, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Oct 11, 2024 | Oct 11, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 15, 2024 | Oct 15, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 15, 2024 | Oct 17, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 15, 2024 | Oct 16, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 16, 2024 | Oct 16, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 12, 2024 | Nov 12, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 12, 2024 | Nov 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 13, 2024 | Nov 13, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Nov 13, 2024 | Nov 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 14, 2024 | Nov 14, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 14, 2024 | Nov 14, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 15, 2024 | Nov 15, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 26, 2024 | Nov 27, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 26, 2024 | Dec 3, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 26, 2024 | Dec 13, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 26, 2024 | Nov 27, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 26, 2024 | Dec 2, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 27, 2024 | Nov 27, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 27, 2024 | Nov 27, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 9, 2024 | Dec 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 10, 2024 | Dec 12, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Dec 13, 2024 | Dec 18, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $608,622
| Name | Role | License on permit |
|---|---|---|
| Andrew Ross Levine Andy Levine Architect | Architect | C-14090 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S-2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019