3000 16th St
San Francisco permit 202410012056 · Mission
Remodeling vacant retail space into a coffee and juice shop. no structural work. no exterior work.
- Filed
- Jul 28, 2025
- Issued
- Oct 17, 2025 (3 months after filing)
- Completed
- Sep 22, 2026 (11 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 17 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Oct 1, 2024 | Oct 1, 2024 | Approved |
Intake Building Inspection · INTAKE | Oct 1, 2024 | Oct 1, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 1, 2024 | Oct 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 6, 2024 | Nov 6, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 14, 2025 | Jan 14, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2025 | Jan 14, 2025 | Approved |
Intake Building Inspection · INTAKE | Jul 28, 2025 | Jul 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 28, 2025 | Jul 28, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Aug 5, 2025 | Aug 5, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 22, 2025 | Aug 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 22, 2025 | Aug 22, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 28, 2025 | Aug 28, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 16, 2025 | Sep 16, 2025 | Issued Comments |
Public health review Public Health · HEALTH | Sep 16, 2025 | Sep 16, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 17, 2025 | Sep 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 17, 2025 | Oct 17, 2025 | — |
Central Permit Bureau Building Inspection · CPB | Oct 17, 2025 | Oct 17, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $292,338
| Name | Role | License on permit |
|---|---|---|
| Harold Edward Howell Mercury Engr Group | Engineer | C17591 |
| Austin Payne | Engineer | C71212 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026