1580 Valencia St
San Francisco permit 202410022184 · Bernal Heights
6/fl-ti for (n) medical office space
- Filed
- Oct 2, 2024
- Issued
- Nov 5, 2024 (1 month after filing)
- Completed
- Apr 1, 2026 (17 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 12 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 2, 2024 | Oct 2, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 3, 2024 | Oct 3, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 3, 2024 | Oct 3, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 3, 2024 | Oct 3, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Oct 3, 2024 | Oct 3, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Oct 4, 2024 | Oct 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 23, 2024 | Oct 23, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 23, 2024 | Oct 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 23, 2024 | Oct 23, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 24, 2024 | Oct 24, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 24, 2024 | Oct 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 31, 2024 | Nov 5, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1,400,000
| Name | Role | License on permit |
|---|---|---|
| Zahra Mehrnoush Arsanjani Polytech Assoicates | Architect | C21224 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026