2614 Anza St
San Francisco permit 202410032251 · Outer Richmond
Legalize (e) dwelling unit on ground flr/1st flr, 644 sqft unit with 1-bedroom, living room, 1-bathroom, closets and a kitchen. (e) furnaces and water heater relocated to garage. project will not expand building envelope and no work at the front of building.
- Filed
- Oct 17, 2024
- Issued
- Aug 22, 2025 (10 months after filing)
- Completed
- Apr 2, 2026 (7 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 34 stops across 6 departments
- Comments issued
- 9 times, by Building Inspection, Planning, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 2, 2024 | Oct 17, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 9, 2024 | Oct 9, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 10, 2024 | Oct 10, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 16, 2024 | Oct 16, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 17, 2024 | Oct 17, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 17, 2024 | Oct 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 18, 2024 | Nov 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 18, 2024 | Nov 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 18, 2024 | Oct 29, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 18, 2024 | Oct 22, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 18, 2024 | Oct 21, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 18, 2024 | Nov 13, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 18, 2024 | Oct 21, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 18, 2024 | Aug 4, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 30, 2024 | Oct 30, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 6, 2025 | Jun 14, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 6, 2025 | Jun 9, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 6, 2025 | Jun 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 6, 2025 | Jun 9, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jun 6, 2025 | Jun 12, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 6, 2025 | Jun 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 6, 2025 | Jun 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 2, 2025 | Jul 13, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 2, 2025 | Jul 10, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 2, 2025 | Jul 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 2, 2025 | Jul 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 2, 2025 | Jul 3, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 2, 2025 | Aug 4, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 2, 2025 | Jul 2, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 13, 2025 | Jul 13, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 30, 2025 | Aug 4, 2025 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Aug 1, 2025 | Aug 1, 2025 | Administrative |
Development fee collection Building Inspection · DFCU | Aug 4, 2025 | Aug 4, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 4, 2025 | Aug 22, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $158,127
| Name | Role | License on permit |
|---|---|---|
| Dennis Alexander Smith Dennis A. Smith Architect | Architect | C-32605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2008