5000 03rd St
San Francisco permit 202410072392 · Bayview Hunters Point
Ti of (e) single story building with upper storage space remodel includes (2) new accessible restrooms and a new front desk.
- Filed
- Oct 7, 2024
- Issued
- Oct 10, 2024 (within 1 month of filing)
- Completed
- Mar 3, 2025 (5 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Oct 7, 2024 | Oct 7, 2024 | Approved |
Intake Building Inspection · INTAKE | Oct 7, 2024 | Oct 7, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 7, 2024 | Oct 7, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 7, 2024 | Oct 7, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 7, 2024 | Oct 7, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 7, 2024 | Oct 7, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Oct 8, 2024 | Oct 8, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 8, 2024 | Oct 8, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 8, 2024 | Oct 8, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 10, 2024 | Oct 10, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 10, 2024 | Oct 10, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $76,000
| Name | Role | License on permit |
|---|---|---|
| Sheldon Errol Eaton Vicinity Architects | Architect | C36656 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026