167 20th Av
San Francisco permit 202410082505 · Outer Richmond
Front yrd garage add'n: demo (e) planting beds,lighting fixtures,retaining walls,concrete steps and excvation as reqd for new sub-terrianian garage with pour in place concrete walls, stairs and deck. new led lighting, planters and permeable surfaces.
- Filed
- Apr 15, 2025
- Issued
- Jan 20, 2026 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 25 stops across 4 departments
- Comments issued
- 8 times, by Planning, Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 8, 2024 | Oct 8, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 8, 2024 | Oct 8, 2024 | Issued Comments |
Intake Building Inspection · INTAKE | Oct 21, 2024 | Oct 21, 2024 | Administrative |
Intake Building Inspection · INTAKE | Nov 6, 2024 | Nov 6, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 6, 2024 | Nov 6, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 11, 2024 | Nov 11, 2024 | Issued Comments |
Intake Building Inspection · INTAKE | Dec 6, 2024 | Dec 6, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 6, 2024 | Dec 6, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Dec 6, 2024 | Dec 18, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 28, 2025 | Apr 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 15, 2025 | Apr 15, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 15, 2025 | Aug 1, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 15, 2025 | Jun 6, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 15, 2025 | Apr 21, 2025 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2025 | Apr 29, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 15, 2025 | Dec 2, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 21, 2025 | Jun 22, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 29, 2025 | May 12, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 17, 2025 | Jul 30, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 17, 2025 | Jul 21, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 17, 2025 | Jul 23, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 17, 2025 | Aug 8, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Nov 17, 2025 | Nov 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 2, 2025 | Dec 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 2, 2025 | Jan 20, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $130,000
| Name | Role | License on permit |
|---|---|---|
| Juan Manuel Jr Duque Mk Think | Architect | C-34336 |
| Akuavi Hine Murphy Brr Curry Inc | Engineer | S-6470 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Aug 2015