39 Downey St
San Francisco permit 202410082512 · Haight Ashbury
Removal of (e) roof access and rooftop stair penthouse. new access stair from (e) level 3 landing to roof level. new rooftop stair penthouse (73 sf). new private roof deck (320 sf). associated lighting and power (by others).
- Filed
- Oct 31, 2024
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 21 stops across 4 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Oct 8, 2024 | Oct 8, 2024 | Approved |
Intake Building Inspection · INTAKE | Oct 8, 2024 | Oct 8, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 8, 2024 | Oct 8, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Oct 10, 2024 | Oct 25, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 17, 2024 | Oct 17, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 17, 2024 | Oct 17, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 22, 2024 | Oct 22, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 23, 2024 | Oct 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 28, 2024 | Nov 4, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 4, 2024 | Nov 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 4, 2024 | Dec 4, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 4, 2024 | Jan 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 4, 2024 | Nov 18, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 4, 2024 | Nov 13, 2024 | Not Applicable |
Fire prevention review Fire Department · SFFD | Nov 4, 2024 | Dec 5, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 4, 2024 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $25,000
| Name | Role | License on permit |
|---|---|---|
| James David Whitfield Whitfield Architects | Architect | C-31997 |
| Michael Chan Michael Chan Company | Engineer | C72969 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026