3806 Clay St
San Francisco permit 202410082572 · Presidio Heights
Interior remodel of (e) 3 story include removal & install (e) structural & non-sturctural interior walls. new bathroom on basement. reconfigure kitchen on level 1, 2. new bathroom & new laundry room on level 2. new attic access stair & finished new media room. storage space @ attic.
- Filed
- Dec 13, 2024
- Issued
- Jun 4, 2025 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 34 stops across 6 departments
- Comments issued
- 9 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 8, 2024 | Oct 8, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 8, 2024 | Oct 8, 2024 | Approved |
Intake Building Inspection · INTAKE | Oct 21, 2024 | Oct 21, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 21, 2024 | Oct 21, 2024 | Approved |
Intake Building Inspection · INTAKE | Oct 24, 2024 | Oct 24, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 24, 2024 | Oct 24, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Oct 25, 2024 | Nov 6, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 1, 2024 | Nov 1, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Nov 4, 2024 | Nov 4, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 5, 2024 | Nov 5, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 6, 2024 | Nov 6, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 27, 2024 | Dec 13, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Dec 10, 2024 | Dec 10, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Dec 12, 2024 | Dec 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 13, 2024 | Dec 13, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 16, 2024 | Dec 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 16, 2024 | Feb 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 16, 2024 | Dec 26, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 16, 2024 | Dec 17, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 16, 2024 | Dec 17, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 16, 2024 | Dec 31, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 16, 2024 | May 21, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 11, 2025 | Mar 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 13, 2025 | Mar 13, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 17, 2025 | Mar 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 17, 2025 | Mar 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 9, 2025 | Apr 14, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 6, 2025 | May 6, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 6, 2025 | May 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 6, 2025 | May 21, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 6, 2025 | May 9, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 6, 2025 | May 21, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 6, 2025 | May 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 21, 2025 | Jun 4, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,145,000
| Name | Role | License on permit |
|---|---|---|
| Matthew Alexander Ininns Mist Architects | Architect | C37517 |
| Engin Yagmur Ecr Engineering | Engineer | C76016 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023