2106 A Larkin St
San Francisco permit 202410092595 · Russian Hill
Add new 475 sq.ft. state adu to rear of first floor. new kitchen. new bath. new w/d.
- Filed
- Nov 21, 2024
- Issued
- Nov 10, 2025 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 39 stops across 6 departments
- Comments issued
- 14 times, by Permit Center, Building Inspection, Planning, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 7, 2024 | Oct 17, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 10, 2024 | Oct 10, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Oct 15, 2024 | Oct 15, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 17, 2024 | Oct 17, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Oct 28, 2024 | Nov 12, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 4, 2024 | Nov 4, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 7, 2024 | Nov 7, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 8, 2024 | Nov 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 13, 2024 | Nov 21, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 22, 2024 | Dec 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 22, 2024 | Dec 2, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 22, 2024 | Dec 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 22, 2024 | Nov 26, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 22, 2024 | Nov 25, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 22, 2024 | Nov 27, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Nov 22, 2024 | Dec 3, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 22, 2024 | Dec 4, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 22, 2024 | Oct 29, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Dec 9, 2024 | Dec 9, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 16, 2025 | Sep 30, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 16, 2025 | Sep 17, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 16, 2025 | Sep 25, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 16, 2025 | Oct 1, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 16, 2025 | Sep 18, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 16, 2025 | Sep 22, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 16, 2025 | Sep 16, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 16, 2025 | Sep 19, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 19, 2025 | Sep 19, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 10, 2025 | Oct 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 10, 2025 | Oct 28, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 10, 2025 | Oct 27, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 10, 2025 | Oct 28, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 10, 2025 | Oct 14, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Oct 10, 2025 | Oct 14, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 10, 2025 | Oct 14, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 10, 2025 | Oct 15, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Oct 28, 2025 | Oct 28, 2025 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Oct 29, 2025 | Oct 29, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 29, 2025 | Nov 10, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $55,000
| Name | Role | License on permit |
|---|---|---|
| Daniel Barringer Barringer Design | Engineer | C68258 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025