879 26th Av
San Francisco permit 202410152964 · Outer Richmond
Remodel of a single family residence into 2 units. one story vertical addition (3rd story). new windows ,exterior/interior doors, skylgihts, interior stairs, hvac, electrical, plumbing and lift.
- Filed
- Oct 28, 2024
- Issued
- May 29, 2025 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 37 stops across 5 departments
- Comments issued
- 13 times, by Building Inspection, Public Works, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 10, 2024 | Oct 28, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 17, 2024 | Oct 17, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 17, 2024 | Oct 17, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 23, 2024 | Oct 23, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 28, 2024 | Oct 28, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 28, 2024 | Oct 29, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 29, 2024 | Dec 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 29, 2024 | Nov 8, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 29, 2024 | Nov 8, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 29, 2024 | Oct 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 29, 2024 | Oct 30, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Oct 29, 2024 | Dec 23, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 29, 2024 | May 19, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Nov 1, 2024 | Dec 27, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2025 | Jan 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 5, 2025 | Feb 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 5, 2025 | Feb 20, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 5, 2025 | Feb 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 5, 2025 | Feb 26, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 5, 2025 | Feb 6, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 5, 2025 | Feb 6, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Feb 5, 2025 | Mar 27, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 5, 2025 | Mar 5, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 1, 2025 | Apr 1, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 10, 2025 | Apr 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2025 | Apr 14, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 10, 2025 | Apr 22, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2025 | Apr 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 10, 2025 | Apr 11, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2025 | Apr 17, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 10, 2025 | Apr 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 15, 2025 | Apr 15, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 29, 2025 | Apr 30, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 30, 2025 | Apr 30, 2025 | Issued Comments |
Development fee collection Building Inspection · DFCU | Apr 30, 2025 | May 16, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 5, 2025 | May 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 19, 2025 | May 29, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $375,379
| Name | Role | License on permit |
|---|---|---|
| Mark Douglas Brand Mark Brand Architecture | Architect | C-13145 |
| Joe Terhemen Igber Sedr Consulting | Engineer | C78132 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025