1 Harrison St
San Francisco permit 202410173107 · Financial District/South Beach
Horizontal infill of (e) terraces at levels 2-5, (n) marquee. architectural and mep core and shell updates at all floors, and (n) interior & exterior assembly amenity spaces at level 6. soft demo, interior tenant improvements, and voluntary seismic upgrade to be done under separate permits.
- Filed
- Nov 14, 2024
- Issued
- Jul 24, 2025 (8 months after filing)
- Completed
- Oct 20, 2026 (15 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 34 stops across 6 departments
- Comments issued
- 11 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 17, 2024 | Oct 17, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 17, 2024 | Oct 17, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Oct 22, 2024 | Nov 8, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 25, 2024 | Oct 25, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 31, 2024 | Oct 31, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 1, 2024 | Nov 1, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 8, 2024 | Nov 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 14, 2024 | Nov 14, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 14, 2024 | Jul 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 14, 2024 | Jan 29, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 14, 2024 | Mar 24, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 14, 2024 | Nov 21, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 14, 2024 | Dec 30, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 14, 2024 | Nov 21, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 14, 2024 | Dec 4, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 14, 2024 | Jul 17, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2024 | Dec 5, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Feb 12, 2025 | Feb 26, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 13, 2025 | Feb 13, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2025 | Mar 3, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 31, 2025 | Jul 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 8, 2025 | Apr 14, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 9, 2025 | Apr 9, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 14, 2025 | Jun 3, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 3, 2025 | Jun 3, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Jun 26, 2025 | Jul 3, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jun 30, 2025 | Jun 30, 2025 | Not Applicable |
Fire prevention review Fire Department · SFFD | Jul 9, 2025 | Jul 9, 2025 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Jul 11, 2025 | Jul 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 11, 2025 | Jul 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 11, 2025 | Jul 15, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 12, 2025 | Jul 16, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 15, 2025 | Jul 15, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 17, 2025 | Jul 24, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $13,300,000
| Name | Role | License on permit |
|---|---|---|
| Marc Pfenninger Sutdios Architecture | Architect | C-27880 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026