871 Turk St
San Francisco permit 202410183281 · Western Addition
Updating mechanical, electrical and plumbing systems in an existing apartment building and including structural supports. all work to incur in common area
- Filed
- Oct 18, 2024
- Issued
- Dec 6, 2024 (2 months after filing)
- Completed
- Feb 4, 2026 (14 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 14 stops across 3 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Oct 18, 2024 | Oct 18, 2024 | Administrative |
Intake Building Inspection · INTAKE | Oct 18, 2024 | Oct 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 18, 2024 | Oct 18, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Oct 18, 2024 | Oct 18, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 18, 2024 | Oct 18, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 18, 2024 | Oct 18, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 18, 2024 | Oct 18, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 1, 2024 | Nov 1, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 1, 2024 | Nov 1, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 5, 2024 | Nov 5, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 18, 2024 | Nov 18, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 18, 2024 | Nov 18, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 18, 2024 | Nov 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 6, 2024 | Dec 6, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Narasimha D Prasanth Tanikella | Engineer | S6568 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025