472 Clipper St
San Francisco permit 202410223447 · Noe Valley
Renovation of 2 family residence including a new dormer and relocated bathroom at level 4 and a remodeled kitchen bath and relocated bedroom at level 3
- Filed
- Nov 20, 2024
- Issued
- Apr 7, 2025 (5 months after filing)
- Completed
- Mar 24, 2026 (12 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 26 stops across 6 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 22, 2024 | Oct 22, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 22, 2024 | Oct 22, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 22, 2024 | Oct 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 22, 2024 | Oct 22, 2024 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Oct 22, 2024 | Oct 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 24, 2024 | Oct 24, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Oct 28, 2024 | Nov 18, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 5, 2024 | Nov 5, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 7, 2024 | Nov 7, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 12, 2024 | Nov 12, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Nov 18, 2024 | Nov 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 20, 2024 | Nov 21, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 21, 2024 | Nov 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 21, 2024 | Jan 21, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 21, 2024 | Dec 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 21, 2024 | Nov 22, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 21, 2024 | Nov 25, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 21, 2024 | Dec 5, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 21, 2024 | Feb 28, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 12, 2025 | Feb 18, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 12, 2025 | Feb 19, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2025 | Feb 25, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 12, 2025 | Feb 13, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2025 | Feb 13, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2025 | Feb 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 28, 2025 | Apr 7, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $220,000
| Name | Role | License on permit |
|---|---|---|
| Todd Neil Bennett Parcel Projects | Architect | C36883 |
| Lawrence Tik Man Wong L Wong Engineering | Engineer | 5135 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025