As written on the permit application.

Remodel (e) kitchen and 2.5 bathrooms. add (2) bathrooms at 2/f. remodel kitchenette/wet bar and a voluntary seismic upgrade.

Timeline
Key dates from the city record.
Filed
Jan 9, 2025
Issued
Jul 28, 2025 (7 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 3 departments
Comments issued
7 times, by Permit Center, Building Inspection
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Oct 23, 2024Administrative

Permit Center

Permit Center · PERMIT-CTR

Nov 25, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jan 2, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jan 10, 2025Administrative

Building plan review

Building Inspection · BLDG

Feb 12, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 28, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jan 24, 2025Approved

Permit Processing Center

Building Inspection · PPC

Jul 17, 2025Administrative

Building plan review

Building Inspection · BLDG

Jun 3, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 18, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 2, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 11, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 11, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 13, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 18, 2025Approved

Building plan review

Building Inspection · BLDG

Jul 3, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 27, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 25, 2025Approved

Building plan review

Building Inspection · BLDG

Jul 8, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 9, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jul 17, 2025Approved

Building plan review

Building Inspection · BLDG

Jul 14, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 14, 2025Approved

Building plan review

Building Inspection · BLDG

Jul 15, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 15, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 28, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$400,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Alan Mark WaldmanEngineer38905
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202410233557 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record