300 Beale St #601
San Francisco permit 202410233588 · Financial District/South Beach
Interior remodel of (1) bathroom, and kitchen with new layout. removal of (e) non bearing walls and install of (n) interior partitoin walls. removal of (e) fireplace, new lighting and switches per plan.
- Filed
- Oct 23, 2024
- Issued
- Nov 18, 2024 (within 1 month of filing)
- Completed
- Jan 16, 2026 (14 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 9 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Oct 23, 2024 | Oct 23, 2024 | Administrative |
Intake Building Inspection · INTAKE | Oct 23, 2024 | Oct 23, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 23, 2024 | Oct 23, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 23, 2024 | Oct 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 23, 2024 | Oct 23, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 24, 2024 | Oct 24, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 24, 2024 | Oct 24, 2024 | Approved |
Public health review Public Health · HEALTH | Oct 24, 2024 | Oct 24, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 18, 2024 | Nov 18, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $470,000
| Name | Role | License on permit |
|---|---|---|
| Robert Gerson Siol | Architect | C33297 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026