San Francisco permit 202410243619 · Outer Richmond
Demolition of rear yard addition & deck, new rear yard addition of 1 stories & ground floor, including 1 bedroom, 2 bath.
- Filed
- Dec 14, 2024
- Issued
- Oct 14, 2025 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 32 stops across 6 departments
- Comments issued
- 11 times, by Permit Center, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 17, 2024 | Nov 1, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Oct 24, 2024 | Dec 16, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 25, 2024 | Oct 25, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 25, 2024 | Oct 25, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Oct 28, 2024 | Oct 28, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 12, 2024 | Dec 5, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 20, 2024 | Nov 20, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Dec 4, 2024 | Dec 4, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 16, 2024 | Jan 7, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 16, 2024 | Jan 30, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 16, 2024 | Dec 24, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 16, 2024 | Jan 3, 2025 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Dec 16, 2024 | Dec 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 16, 2024 | Dec 31, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 16, 2024 | Sep 9, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | May 15, 2025 | Jun 17, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 15, 2025 | May 15, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 20, 2025 | May 27, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 20, 2025 | May 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 27, 2025 | Jul 1, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 3, 2025 | Jul 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 15, 2025 | Jul 23, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 15, 2025 | Jul 31, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 15, 2025 | Jul 23, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 18, 2025 | Jul 18, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 21, 2025 | Jul 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 23, 2025 | Jul 23, 2025 | Approved |
Zoning review Planning · CP-ZOC | Aug 1, 2025 | Aug 13, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 1, 2025 | Aug 8, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 14, 2025 | Oct 14, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | Aug 15, 2025 | Aug 21, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 25, 2025 | Sep 9, 2025 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Paul Chan Pctc Engineering | Engineer | C59840 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022