Demolition of rear yard addition & deck, new rear yard addition of 1 stories & ground floor, including 1 bedroom, 2 bath.

Timeline
Key dates from the city record.
Filed
Dec 14, 2024
Issued
Oct 14, 2025 (10 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
32 stops across 6 departments
Comments issued
11 times, by Permit Center, Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Nov 1, 2024Issued Comments

Central Permit Bureau

Building Inspection · CPB

Dec 16, 2024Administrative

Mechanical pre-screening

Building Inspection · PRE-MECH

Oct 25, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Oct 25, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Oct 28, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Dec 5, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Nov 20, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Dec 4, 2024Approved

Zoning review

Planning · CP-ZOC

Jan 7, 2025Approved

Building plan review

Building Inspection · BLDG

Jan 30, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 24, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 3, 2025Not Applicable

Street use and mapping

Public Works · DPW-BSM

Dec 19, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 31, 2024Approved

Permit Processing Center

Building Inspection · PPC

Sep 9, 2025Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jun 17, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

May 15, 2025Issued Comments

Building plan review

Building Inspection · BLDG

May 27, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

May 27, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 1, 2025Approved

Zoning review

Planning · CP-ZOC

Jul 3, 2025Approved

Building plan review

Building Inspection · BLDG

Jul 23, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 31, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jul 23, 2025Approved

Fire prevention review

Fire Department · SFFD

Jul 18, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jul 21, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jul 23, 2025Approved

Zoning review

Planning · CP-ZOC

Aug 13, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 8, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Oct 14, 2025Administrative

Urban forestry

Public Works · DPW-BUF

Aug 21, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Sep 9, 2025Approved

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$300,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Paul Chan

Pctc Engineering

EngineerC59840
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202410243619 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record